Update On Construction Activities At Longonjo

Civil works for the 350 person camp, rehabilitation of the access road and agricultural demonstration plots ahead of main construction.

Pensana is pleased to provide the following update on activities at the Longonjo minesite ahead of main construction.

As previously announced the early-stage development activities are being funded by a US$15 million bridging loan provided by FSDEA (the Angolan Sovereign Wealth Fund) ahead of the main finance.

The significant activities have been the civil works for the camp, the rehabilitation of the access road to the Longonjo railway station and the agricultural demonstration plots under the Livelihood Restoration Programme.

The 4.5 kilometre road linking the site to the Benguela railway line has been upgraded. The enhanced road features include an improved roadbed substructure, a redefined road profile and rapid drainage systems.

Serving as the primary route for inbound materials during construction and later for reagent import and the export of Mixed Rare Earth Carbonate in containers, the road connects the mine to the Longonjo station for rail access to the port of Lobito for shipping.

The Benguela railway line is part of the Lobito corridor undergoing a US$550 million investment from the US Government. The investment aims to secure critical minerals across central Africa to be exported via the port of Lobito and is anticipated to become one of Africa’s most important rail transport systems.

Several kilometres of overhead powerlines, together with an underground water supply and effluent disposal system have been installed ahead of the arrival of the 350-person modular camp, which has been assembled at Johannesburg and is being relocated to site. The camp will be the primary operations base for the construction team.

Agricultural demonstration plots have been established by South African agriculture consultants, Vuna Agri, as part of the Livelihood Restoration Programme. The demonstration plots have an area of nine hectares and have now successfully completed their first full season. The Livelihood Restoration Programme was established to provide replacement land for any displaced farmers and additionally to provide a training base for those persons affected by the project to develop their agricultural skill sets.

The objective is to help local growers and farmers create healthy and sustainable agro-ecosystems, boosting household income in nearby communities, whilst enhancing overall food security. This ongoing programme is being conducted in collaboration with local universities with a view to continually improving farming practices.

“We now have over 50 engineering contractors and Longonjo staff working on site in preparation for the commencement of main construction. There has been a very positive reaction to the activities on site amongst the local community, in particular with the creation of well-paid jobs and the successful implementation of the first phase of the livelihood restoration programme.

We have a strong team supporting the main construction which is being manged by MCC a leading project management team with a track record of delivering projects across Africa, including Angola. ADP, the main contractor is an African minerals specialist in the detailed design, construction and commissioning of modular mineral processing plants with extensive development experience in Angola.” – Tim George CEO

Item 2

Contributor:

Web

Content Visibility:

SEO Title
Pensana's Update on Longonjo Mine Construction: Advancing Infrastructure and Community Engagement
SEO Description
Pensana provides an update on construction activities at the Longonjo minesite, highlighting progress ahead of main construction. Funded by a US$15 million loan from FSDEA, significant developments include civil works for the camp, access road rehabilitation, and agricultural demonstration plots. The upgraded 4.5 km road links to the Benguela railway, integral for material transport and export. The Lobito corridor's US$550 million investment underscores its future significance in Africa’s rail transport. Pensana's collaboration with local communities and universities aims to enhance agricultural skills and boost local economies.
SEO Keywords


SEO Keyphrase
  • Angola
Item 2

Exciting developments are underway at the Longonjo minesite, with Pensana reporting significant progress in preparation for the main construction phase. This follows the early-stage development activities funded by a US$15 million loan from FSDEA.

Highlights Include:

  • Completion of civil works for the camp.
  • Rehabilitation of the access road connecting to the Longonjo railway station.
  • Upgrading of a 4.5 km road linking the site to the Benguela railway, crucial for material transport during construction and later for exporting Mixed Rare Earth Carbonate.

The Benguela railway line, part of the strategic Lobito corridor, positioning the corridor as a key player in Africa’s rail transport system. This aligns with #Pensana’s efforts in fostering sustainable mining and community development.

#LongonjoMine #Railway #rail #Africa #Mining Development #Infrastructure #Investment

Twitter:

Update on Longonjo Mine: Pensana reports significant progress pre-main construction.

  • Camp civil works & road to Longonjo railway station rehab.
  • 5 km road upgrade for vital rail link.

#LongonjoMine #RailInfrastructure #Mining

 